Public Comment Period - Draft Modification of the Industrial Stormwater General Permit

3 Results

Sort:

Comment From: Puget Soundkeeper Alliance (Kathryn Rizzo)

10/02/26 @ 2:30 PM
PSK incorporates the attached comments.
Attachments:

Comment From: James Bishop

9/23/26 @ 2:11 PM
The current general permit cycle is every five years. Looking ahead, if the expiry date is moved to December 31, 2028, will four years become the new standard permit term (2033, 2037), or will the cycle revert to five years to maintain the intended o...↓
No attachments

Comment From: Geosyntec Consultants (Joel Prock)

9/23/26 @ 11:00 AM
Special Conditions S6.C.2.d. and S6.C.2.e. identify May 15, 2029, as the due date for line cleaning waivers and storm drain solids sampling and analysis waivers, respectively. Ecology's proposed modification of the Industrial Stormwater General Permi...↓