The following comments were submitted (copy & pasted) to the State Department of Ecology website on behalf of Carole DeGrave and Friends of Rocky Top (FORT), a CascadiaNOW! sponsored project, regarding the Agreed Order between Ecology and DTG/Anderso...↓
The background information on the DTG/Anderson site in the Agreed Order begins in 1997, yet disposal at Rocky Top is known to have occurred a decade earlier. To understand the scope of actual potential contamination threat from this location, the background section needs to be revised to reflect the site's complete disposal history.
Note: The Macquarie Asset Management purchase of all of DTG's assets, announced Dec. 1, 2022, requires acknowledgement in the AO and in all future documents. In these comments, for brevity and convenience, the term Anderson Site refers to all facilities and operations on Rocky Top owned and operated today by Macquarie/DTG.
Anderson Site History
A special property use permit was issued July 18, 1983, to Ron Anderson for surface mining permit (SPU-27-1983; Permit #675) for 10 acres, with expiration set for December 31, 2003.
A second special use permit was issued in 1987, allowing establishment of an asphalt plant and increasing the amount of material allowed to be mined (SPU-21-87; Permit #906).
In 1988, the Yakima Health District permitted disposal of demolition waste in the Anderson Site unlined surface mining pits located near the intersection of Summitview Rd and Rocky Top Road, as evidenced by multiple sources including:
a. Yakima County code enforcement officer complaints reporting demolition pit fires in July 1989 (see Swackhammer ERTS complaints),
b. Yakima County Planning Department approval of Anderson's Sanitary Landfill to Process Contaminated Soil (SPU-41-91), 4. Current Zoning and Use which states:
There are three quarries operated by the applicant in the vicinity, and two additional quarries operated by others to east across Summitview Road. The applicant's pit located at the northwest corner of Summitview and Rocky Top Roads is being refilled with waste materials from the demolition of buildings. A solid waste permit was issued by the Yakima Health District for this purpose.
And under 5. Project Description
Soil contaminated by petroleum products is brought to the site for treatment, where it is spread, aerated, and retested until it meets state clean-up standards for "problem wastes". The soils are then either used as a cover for the existing construction waste disposal pit on the site or crushed on site for use in making asphalt.
This site has been licensed since 1989 by the Washington State Dept. of Ecology. Originally DOE controlled operation of the site because the regulatory framework had not yet been established as to how to deal with this new activity. Now DOE is transferring control with respect to permitting the land use to the local jurisdiction, being Yakima County in this instance, and is also remanding control to the Yakima Health District with respect to monitoring the operation and issuing a solid waste permit. Accordingly, this permit is simply to replace the current regulatory framework.
Anderson Rock & Demolition Pits, Sanitary Landfill to Process Contaminated Soil
Yakima County Special Permit Use SPU-41-91, Zoning Adjustor's Decision, Sept. 12, 1991
As described above, the unlined demolition pits were originally "licensed" by Ecology and receiving waste in 1988, with permit authority transferred to Yakima Health District that year. In 1991, the demolition pits were permitted to be covered with remediated PCS.
What makes the unlined demolition pits a growing concern is the fact that material disposed was marginally regulated and routinely reported on fire, requiring dousing with water and their proximity to Cowiche Creek. Putting landfill fires out with water increases the potential to drive contaminants into the subsurface and groundwater resources. The burned material may have included tires, which along with roadway tire dust, can leach a toxic chemical; 6PPD-quinone. According to Ecology, tires release this toxin that ends up in roadway dust, and via water, can enter stormwater systems, drainage areas, groundwater, and sources that feed creeks and streams (see Attachment #1 Ecology news release, Saving Washington's salmon from toxic tire dust, January 25, 2023).
As regulator's are aware, no groundwater monitoring wells were ever required or established for the pits which are closer to Cowiche Creek than the LPL MTCA site or the PCS facility. In recent years the Yakama Nation have re-introduced salmon into this stretch of the river.
In 1991 the County approved Anderson's unlined Petroleum Contaminated Soil (PCS) remediation facility that accepted contaminated soils from all over the state, including Puget Sound and the Yakima Training Center (YTC). As Ecology recently disclosed in a letter to the Yakima Health District, this included 743 cubic yards of PFAS contaminated soil in 2004 for remediation and landfill use and/or disposal (see Attachment #2, Rivard letter to YHD, Jan 19, 2023).
Consequently, the unlined demolition pits at/near the current office, and the unlined PCS remediation site have never been included in the Anderson Site groundwater monitoring system, which started in 2006 with two wells completed in separate water bearing zones. A third monitoring well was completed in a separate, third water bearing zone in July 2022. Drilling was halted in a fourth monitoring well by DTG because of 'budget' concerns, ending the company's field investigation and further delaying their chances to provide a plan that meets the requirements of WAC 173-350-500.
Facility regulators and the public should be aware that it was at this same time - July 2022 - that DTG was negotiating its acquisition by Macquarie Asset Management for all of the company's assets, including a landfill on fire and emanating toxic fumes, that would shortly be forced into the Model Toxic Control Act cleanup program.
It should be recognized that five months prior the company claimed to Rivard and landfill regulators that it was "eager to develop a concrete action plan to work with Yakima Health to address the points in your February 11, 2022 letter" (see Attachment #3, John Martin email to James Rivard, re DTG Yakima LPL � Virtual Review Meeting, February 15, 2022 9:40:18 AM and Attachment #4 James Rivard letter to Shawn Magee, YHD, re DTG LPL New Cell Development � Hydrogeology Comments, February 11, 2022 letter).
Rivard's letter lays bare the wholly inadequate site characterization and groundwater interpretations, and that the existing monitoring network does not meet WAC 173-350-500 requirements, and recommends DTG conduct additional field work, including drilling multiple wells. While Martin committed to regulators that his company was eager to do just that, the reality is DTG was more committed to delay this work until now, Spring 2023, three months before a June 30, 2023 deadline to meet the regulator's concerns for landfill permit approval, per the YHD's letter to DTG outlining required tasks, and schedule for product development, March 24, 2022.
In July 2022 DTG ends their "concrete action plan" after drilling one well (50 feet) and stopping drilling of a second well due to budget implications. By not conducting the required field investigation DTG ignored regulator's timetable and requirements for field data it appears because of the potential revenue implications during negotiations with Macquarie. The company delayed drilling and field work until a timely and stern reprimand from the YHD (see Attachment #5, Steven Newchurch letter to John Martin, Additional Hydrogeologic Investigative Requirements for DTG LPL Permit Renewal and Southern Expansion, February 27, 2023).
The point is, the record is clear; it was 13 months after Martin told regulators the company was "eager to develop a concrete action plan" to address Ecology's list of hydrogeology concerns that the company actually provides regulators with a reasonable plan to do so that is only now being implemented.
The Anderson Site history of unlined, unmonitored disposal operations married with operational mismanagement and a 300% increase in disposal under DTG's three-year ownership that generated hundreds of complaints and confirmed multiple facility violations (see ERTS Anderson Site complaints record, and YHD Quarterly Inspection reports; 2020-2023) complicate regulator's ability to understand the web of contributing factors to detection of groundwater contamination at this location.
Consequently, the background information should be revised to include the contamination threat posed by the multiple permitted facilities because of their known, or suspected potential to contribute to Anderson Site groundwater contamination, including:
1) unlined & unmonitored petroleum contaminated soil (PCS) remediation site,
2) PFAS/PCS threat to groundwater not included,
3) unlined demolition waste pits (and subsequent fires),
4) unlined Material Recovery Facility (MRF) operating on unlined landfill working face,
5) disposal of gypsum and gypsum by-products, and
6) suspected disposal in the unlined surface mining area
Combined, these multiple factors (discussed individually below) suggest a broader, more significant, and complicated threat to local drinking water supplies than represented in the limited scope of the initial MTCA investigation. An argument can be made that multiple unlined, overlapping disposal operations where remediated PCS is allowed for use and disposal throughout the facility raises complex and challenging questions for determining a specific source for detected contaminates.
How will regulators parse which facility and flow path detected sources of contamination originate?
Is a detected contaminant the by-product of: a fire at one of the demolition pits that were doused with water?
Or from the MRF operating at the working face without a liner?
Or from the PFAS contaminated PCS soils from the Yakima Training Center disposed and spread around the site in 2004-06?
Or from other soils stored at the PCS site which may or may not have been contaminated, but which were moved to other parts of the facility in fall and winter of 2022/23?
Or maybe the contaminant's chemistry reflects the Elliot Bay seawall dredge spoils remediated and disposed, beginning in 2015? Would the detection be from the PCS site or the LPL MTCA footprint?
How can the public have confidence in the ability of this company or regulators to determine the source of detected contamination when there are many known potential sources that could be, either alone or combined, responsible for the detection?
As MTCA allows, the information generated during the investigation is added and if required, the scope can be reconsidered to reflect the new information and understanding of site conditions. While we understand why the initial MTCA footprint is limited, we think that the extent of contamination likely at this location makes it inevitable that regulators will be forced to require a broader investigation that includes all of these known potential sources of contamination, and expanding the MTCA footprint accordingly.
Comments on each contamination source that should be included in the MTCA investigation:
1) Unlined and unmonitored PCS site
The 1990-91 Anderson PCS permit application proposed three - or more - monitoring wells. While the County approval required three (3) groundwater monitoring wells, to date, facility regulators have not required any groundwater monitoring wells for this unlined facility that has been in operation for over 30 years.
2) PCS and PFAS threat to groundwater not included
It was recently reported that a U.S. EPA survey of 200 municipal solid waste (MSW) landfills found PFAS in the leachate of 95% of them. Landfills and material recovery facilities (MRFs) are known "passive receivers" of PFAS- containing items. DTG has transferred material to Rocky Top for many years, primarily from MRFs in Puget Sound. Building materials permitted for disposal at Rocky Top have likely contained PFAS. DTG ramped up acquisition of Puget Sound MRFs from late 2020 to early 2023 (15 companies, multiple locations, transfer vehicles, collection containers, etc.) that allowed them to substantially increase waste flow to Yakima in 2021 and 2022.
Consequently, it could be that PFAS contaminated materials and soils have been remediated, used and/or disposed on Rocky Top from demolition pits in the late 1980s, the permitted 1997 Demolition Waste landfill, and permitted LPLs in 2007 & 2015 (historical fill area).
This doesn't include the area YHD allowed DTG to fill just south of the historical fill, where DTG excavated the Vantage Interbed to gain airspace and eliminated the approved natural soil liner. This area has likely received over 500,000 cy of PFAS contaminated waste, covered by PCS soil that may or may not have been remediated.
Consequently, it is challenging to ascertain the PFAS threat and potential risk of future groundwater contamination at this location without new air and water quality data and continue technical review of site records. Why are PFAS called 'forever chemicals'? According to the Academy of Sciences:
Perfluoroalkyl and polyfluoroalkyl substances (PFAS) are a class of chemicals that includes more than 12,000 different compounds with various chemical properties. PFAS are commonly used in thousands of products, from nonstick cookware to firefighting foams and protective gear, because they have desirable chemical properties that impart oil and water repellency, friction reduction, and temperature resistance. PFAS as a class have a wide variety of distinct chemical properties and toxicities; for example, some PFAS can bioaccumulate and persist in the human body and the environment, while others transform relatively quickly. The PFAS that do transform, however, will become one or more other PFAS because the carbon�fluorine bond they contain does not break naturally. It is for this reason that PFAS are termed "forever chemicals."
Summary, National Academy of Sciences, 2022
Guidance on PFAS Exposure, Testing, and Clinical Follow-Up
3) Demolition Pits and recorded fires threat to groundwater not included
This long history of PCS and demolition, now construction waste that likely contain PFAS contaminated materials and soils remediated and used and/or disposed on Rocky Top at demolition pits in the late 1980s, in the permitted 1997 Demolition Waste landfill, and the permitted LPLs in 2007 & 2015 (including historical fill area).
Lastly, because the YHD allowed DTG to place waste south of the historical fill, where DTG excavated the Vantage Interbed to gain airspace and eliminated the YHD approved natural soil liner that protected groundwater from landfill leachate. This unlined area has likely received over 500,000 cy of material in 2022, including PFAS contaminated materials covered by PCS soil that may or may not have been remediated.
Consequently, it will be challenging for regulators to ascertain the source of the two identified contaminants (Polycyclic Aromatic Hydrocarbons and Benzene) and suspected PCS contamination without expanding the site investigation to account for the existing potential sources of contamination � the demolition pits, PCS site and mining area.
4) MRF threat to groundwater not included
In addition, the background should include the permitted material recovery facility (MRF) operations because they were allowed to operate on the unlined landfill working face (not an impervious surface as standard) including in the MTCA area under investigation.
The MRF continues to operate on the unlined cell south of the historical cell, not an impervious surface, that constitutes an increased risk because DTG excavated portions of the approved natural soil layer (Vantage Interbed), likely creating more direct pathways for contamination to reach local groundwater (drinking water supply) and nearby Cowiche Creek.
5) Disposal of gypsum and gypsum by-products
In recent years, disposal of drywall and gypsum in landfills has been banned in Canada and municipalities across our nation due to the highly toxic hydrogen sulfide gas that is generated from the combination of drywall waste (gypsum), organic material, and a landfill's anerobic (air free) environment.
Shortly after acquiring the Anderson operations, DTG began importing significant volumes of "drywall backing paper" from Canada, reporting 19,394 cy in 2020, and 164,400 cy in 2021. Neighbors provided regulators with photos of this material spread like a blanket across the LPL in 2021. As DTG acknowledges, in 2021, YHD received odor complaints and observed visual vapor plumes emanating from fissures within the landfill. The amount of gypsum disposed at this facility is far greater than the Canada waste stream, as new information has recently surfaced drawing regulatory scrutiny in Puget Sound regarding DTG's MRF operations, including suspect gypsum recycling and likely disposal in Yakima. The new information comes from a DTG whistleblower and leading gypsum industry recycler.
6) Suspected disposal in the unlined surface mining area
In addition, suspected disposal in pre-dug holes in the mining area between 9:00 pm and 10:00 pm on April 15 & 16, 2020 was observed by multiple neighbors, and reported to facility regulators (see Cave ERTS complaint). This unexplained late night disposal deserves further investigation and should prevent the planned LPL expansion over the top of this suspected disposal area.
Comments on the Draft Cleanup Action Plan will be submitted separately by Joseph Stolle, PE GeoEngineers.
↓